Kota Stone Flooring

Kota Stone Flooring cost Analysis

Kota Stone installation cost Rate Evaluation of Kota Stone Flooring Materials

The components comprise Kota stone, cement slurry, cement mortars, and dark shade pigment in a black tint.

Kota Stone is necessary:

Rate Analysis of Kota Stone Flooring Materials

The components comprise Kota stone, cement slurry, cement mortars, and dark shade pigment in a black tint.

Kota Stone is required:

10 sq. m. of Kota Stone will be needed for the flooring. However, some stones are lost throughout the moving and placing processes. Therefore, 15% of waste must be included in the estimate. Therefore, 10 Sqm of flooring will need 10+(1015%) = 10+1.5 = 11.5 Sqm of Kota Stone.

Cement required for floors made of Kota Stone:

Making slurry and the basis for 1:4 Cement Mortar both need cement.

Cement slurry for flooring made of Kota Stone:

In the case of bedding, @4.4Kg per Sqm, 10 x 4.4 = 44 Kg It will be necessary to use cement, and 20 Kg of cement will be needed for joints. Therefore, 64 Kg (0.064 tonnes) of cement will be needed in total.

For flooring made of Kota Stone, cement mortar (1:4)

Amount of Cement:

The amount of cement will be 0.268 Cum (26.80% of cement) for 1 Cum of 1:4 Cement Mortar. Cement bags will be 0.268/bag of cement volume.

A bag of cement weighs 50 kilogrammes, thus 7.7 bags would weigh 386 kilogrammes, or 0.38 tonne.

Cement equals 0.38 x 0.20 x 0.076 cum for 10 sqm x 20 mm = 0.2 cum.

Requirment of the Sand:

Sand quantity equals 4 x 0.076 = 0.304 cum for a 1:4 ratio.

Flooring made of Kota Stone needs pigment

To match the slab’s hue, about 4.5 kg of black colour dark shade pigment will be needed.

Workforce needed for laying a floor of kota stone

Mason requirment:

8.33 Sqm of Kota Stone flooring may be laid by a mason each day. Therefore, 1/8.3310=1.2 Masons are needed for 10 Sqm.

Beldar requirment :

1.15 To install 10 Sqm of Kota stone flooring, beldar would be needed.

Coolie requirment:

10 Sqm of Kota stone flooring will need the work of one Coolie.

competent Beldar requirment?

For rubbing Kota stone, five Beldar are needed.

Necessary Machines requirment ?

For rubbing and polishing 10 sqm of Kota Stone, about 4 machines are needed each day.

Cement for floors made of Kota Stone

Making slurry and the basis for 1:4 Cement Mortar both need cement.

Cement slurry for flooring made of Kota Stone

In the case of bedding, @4.4Kg per Sqm, 10 x 4.4 = 44 Kg It will be necessary to use cement, and 20 Kg of cement will be needed for joints. Therefore, 64 Kg (0.064 tonnes) of cement will be needed in total.

For flooring made of Kota Stone, cement mortar (1:4)