Waterproofing Stage Of Construction

Waterproofing Stage Of Construction

What is Waterproofing?

Waterproofing is the process of covering roof surfaces with an impermeable coating to prevent water penetration. When it comes to the last finishing touches on the house, this is the most crucial task. Buildings and other structures need to be waterproofed anywhere that will come into contact with water, including the roof, restrooms, balconies, water tanks, swimming pools, and other areas.

Importance

Flexible waterproofing membranes provide excellent water and humidity protection for walls and floors in bathrooms, basements, balconies, and swimming pools. Durable and sustainable building need this kind of protection. Failure to waterproof will affect or harm other components, such as painting, plastering, and R.C.C. members. This is the reason you should never skimp on waterproofing quality.

Waterproofing

Sub-stages of Waterproofing

Waterproofing is made up of various sub-stages like:

Waterproofing in bathroom and toilets

Waterproofing on terrace

Perfect time to Start

Substructure should be preferably completed before the rainy season to:

The summer is the ideal season to waterproof the patio and other outside areas since it gives the materials plenty of time to dry.

Toilets and bathrooms may have their waterproofing done at any time of the year.

Time required to complete the Waterproofing work

Approx. 4 days for a 750 sq. ft. home and approx. 5 days for a 1000 sq. ft. home

Waterproofing should ideally be the last activity in any building work

Challenges

Preferably, substructure should be finished before the rainy season in order to:

storing various materials in the space that is available, such as excavated earth, cement, sand, aggregates, and reinforcing